AIS Infrastructure is executing the Plant Branch Cells 1–6 project, a large-scale environmental containment initiative for Southern Company focused on the safe management of legacy coal ash materials. This $74M+ project involves the construction of six engineered containment cells designed to meet strict environmental and regulatory standards.
The scope includes mass earthwork, subgrade preparation, and precision clay liner installation to form impermeable barriers for long-term containment. Each clay lift is carefully placed, inspected, and quality-controlled to ensure compliance with permeability requirements before progressing. The project also incorporates geosynthetic clay liners (GCL), along with ongoing work that includes installation of electrical duct banks, force mains, transmission lines, and mechanical systems.