    Los Detalles Del Proyecto

  • Mercado:
  • Ubicación: Franklin, Georgia

Plant Wansley Long Term Gypsum Storage Project

Ámbito de Trabajo:

AIS Infrastructure performed site development and landfill construction for the Plant Wansley Long Term Gypsum Storage Facility. The project included development of one of the largest RCRA Subtitle D landfills in the Southeast, consisting of three HDPE-lined storage cells covering approximately 145 acres.

Detalles:

  • 250 acres de compensación y de arranque
  • 2.8 million cubic yards of excavation
  • La erosión y control de sedimentos de instalación y mantenimiento
  • Placement of 335,000 cubic yards of permeable clay liner
  • Placement of 370,000 tons of sand liner
  • Installation of 18.9 million square feet of geosynthetic liner systems
  • Installation of 21,000 linear feet of HDPE pipe
  • Installation of 28,000 linear feet of leachate trench and 50,000 linear feet of leachate piping
  • Construction of drainage structures and detention ponds
  • Continuous dewatering operations
  • Site security fencing installation